Question: (i) Explain how Takt time contributes to failure in the pursuit of a Lean System? [5 Marks] (ii) Calculate the Takt time (in seconds) for

(i) Explain how Takt time contributes to failure

(i) Explain how Takt time contributes to failure in the pursuit of a Lean System? [5 Marks] (ii) Calculate the Takt time (in seconds) for an 8 hour day operating in a 4 day week, allowing for one 15 minute break, one 20 minute lunch, tidy up time of 5 minutes each day and wellness time of 20 minutes per week. The customer would like to have 10000 parts per week. What is the Takt Rate per week? [5 Marks]