Question: i. Fill out the network diagram table below for the project above. ACTIVITY PRECEDING ACTIVITY NORMAL DURATION NORMAL COST CRASH DURATION CRASH COST CRASH SLOPE
i. Fill out the network diagram table below for the project above. ACTIVITY PRECEDING ACTIVITY NORMAL DURATION NORMAL COST CRASH DURATION CRASH COST CRASH SLOPE COST SLOPE A 5 $ 100.00 4 $ 200.00 B 4 $ 120.00 2 $ 160.00 C A 10 $ 400.00 4 $ 1,000.00 D B 7 $ 300.00 3 $ 700.00 E B 11 $ 200.00 10 $ 250.00 F C 8 $ 400.00 6 $ 800.00 G D,E,F 4 $ 300.00 4 $ 300.00 ii. Find the critical path. iii. Find the normal duration time of the project. iv. Find the cost associated with the normal duration time. v. Find the cost associated with crashing for three days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
