Question: I got a 6 5 on this last module and im looking for some guidance to get it corrected. Step 1 : Using the Apportion

I got a 65 on this last module and im looking for some guidance to get it corrected. Step 1: Using the Apportion Method, create a budget
Total Budget = $85,000
Initial Design Work =10%
Ventilation System =35%(Parts =20%; Labor =15%)
New Racks =20%(Parts =15%; Labor =5%)
Power Supplies and Cables =25%(Parts =15%; Labor =10%)
Switchover Ops Checks =10%
Step 2: Given the budget and schedule details, create a Time Phased Budget (like the one in Fig 8.16). Assume the cost of parts is paid in the first unit of time, and the labor is equally spread out over the units of time.
Total Budget = $85,000
Initial design Work =10%
Ventilation System =35%(Parts =20%; labor =15%)
New Racks =20%(Parts =15%; labor =5%)
Power Supplies and Cables =25%(Parts =15%; labor =10%)
Switchover Ops Checks =10%AT Project Activity Estimates
Critical Path =2,9,15,10,16,17,18, and 19
\table[[,\table[[Activity],[(Bolded is the deliverable)]],\table[[Most Likely Duration],[(unit = days)]],\table[[Immediate],[Predecessor]]],[1,Data Migration Center Project,,],[2,1.1 Team Meeting,1,],[3,1.2 Hire Contractors,7,2],[4,1.3 Network Design,14,2],[5,1.4 Ventilation System,,],[,1.4.1 Order Ventilation System,21,2],[,1.4.2 Install Ventilation System,7,6],[,1.5 New Racks,,],[9,1.5.1 Order Racks,14,2],[10,1.5.2 Install Racks,21,9,15],[11,1.6 Power Supplies and Cables,,],[12,1.6.1 Order Power Supplies and Cables,7,2],[13,1.6.2 Install Power Supplies,5,12,15],[14,1.6.3 Install Cables,8,12,15],[15,1.7 Renovation of Data Center,20,3,4],[16,1.8 City Inspection,2,7,10,13,14
 I got a 65 on this last module and im looking

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!