Question: I got the first two rows correct and getting stuck on rest. Please explain numbers. I think Projected On Hand is 250 for week 1

I got the first two rows correct and getting stuck on rest. Please explain numbers. I think Projected On Hand is 250 for week 1 and 2 and 2000 for week 3, but not sure for rest since there is no more "scheduled receipts, not sure when the order of 300 is received. I am not sure when it is being placed, I thought week 3 when other order comes in. Please provide more feed back. I looked at similar problems but they were not helpful since they didnt explain
Item A has a gross requirement of 2.300 in week 6. Currently, there are 250 Item A's on hand with a scheduled receipt of 1.750 items in week 3. The lead time for item A is 4 weeks with an order quantity of 300. Complete the MRP record for Item A. Complete the MRP record for Item A (enter your responses as whole numbers). 0 1 2 3 4 5 6 Week Item ALT = 4 Quantity: FOQ=300 0 0 2300 Gross Requirements Scheduled Receipts Projected on Hand Net Requirements Planned Order Receipts 2500 DODO DODO 000 DODO ooOODStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts