Question: i , j = 1 , 2 , . . . , 7 . We wish to develop a linear programming model to determine the

i, j =1,2,...,7. We wish to develop a linear programming model to determine the route from the
storage facility to the job site that minimizes the total travel time.
(a) For the LP for the shortest route problem, write the supply (node 1) constraint.
(b) For the LP for the shortest route problem, write the balance constraint for node 4.
(c) For the LP for the shortest route problem, write the demand (node 7) constraint.
You do not need to draw the network diagram, provide the complete LP formulation, or solve the
LP.