Question: I know that expexted time for acticity c is 12 weeks and the variance for acticity C is 1.78 weeks. calculate rest. Options for critcical

I know that expexted time for acticity c is 12 weeks and the variance for acticity C is 1.78 weeks. calculate rest.  I know that expexted time for acticity c is 12 weeks
and the variance for acticity C is 1.78 weeks. calculate rest. Options
Options for critcical path:
for critcical path: Ross Hopkins, president of Hopkins Hospitality, has developed the

Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for buik new motels a) The expected (estimated) time for activity C is weeks. (Round your response to two decimal places.) b) The variance for activity C is weeks. (Round your response to two decimal places.) c) Based on the calculation of the estimated times, the critical path is d) The estimated time for the critical path is weeks. (Round your rosponse to two decimal places.) e) The activity variance along the critical path is weeks. (Round your response to two decimal places.) f) Using the the probability that Hopkins Hospitality will finish the project in 42 weeks or less is (Enteras a probability and round your response to three decimal places.) ACGJKABEFHJKABEFIKADJKACFHJKACFIKABEGJK

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!