Question: I know the right answer but WHY is it the right answer? You are the project manager of a 1 2 0 0 foot ocean
I know the right answer but WHY is it the right answer?
You are the project manager of a foot ocean pier construction project. The project management plan required that you complete the project in weeks at a cost of $ per linear foot. After the th week, the project analyst reports that the project's EV is $ and the total cost to date is $ If you assume that you will continue to spend at the same rate, what is the estimate to complete?
A $
B $
C $ This is the right answer but why is it the right answer?
D $
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock