Question: I may be wrong on what i chose here Question 8/11 You're managing a long-term team project with formally established monthly milestones. You decide to

I may be wrong on what i chose here Question 8/11

I may be wrong on what i chose here

Question 8/11 You're managing a long-term team project with formally established monthly milestones. You decide to check in whh the team weekly for status updates. Which three items below are most critical to discuss during these meetings? Select three answers. Team members' upcoming PTO Roadblocks that may impact the project timeline Additional resource needs Progress toward project milestones Review of the project plan Potential new projects