Question: I. Multiple choice (3 points each) 4 8 7 10 11 2 9 1. Given the portion of the network shown above, what is the

I. Multiple choice (3 points each) 4 8 7 10 11 2
I. Multiple choice (3 points each) 4 8 7 10 11 2 9 1. Given the portion of the network shown above, what is the earliest finish time for activity 10-11 (far right hand side), if the earliest start time of 8-10 (upper left hand side) is 12, and the earliest start time of 9-10 (lower left hand side) is 13? A) 22 B) 23 C) 24 D) 25 E) 26