Question: I need a clear step by step answer please thank you :) Use the following MRP record to answer the following question. ITEM: XYZ Lot
I need a clear step by step answer please
Use the following MRP record to answer the following question. ITEM: XYZ Lot Size P = 2 Description: Lead Time: 1 week Safety Stock 50 Datel 1 23 4 5 6 78 Gross 100 50 70 40 90 50 Requirements Scheduled Receipts 100 Projected on 50 W Hand Planned receipts Planned order releases What is the planned receipts quantity in week 3
thank you :)