Question: I NEED AN ANSWER QUICK! I WILL UPVOTE! 2. A two-station line where station 1 consists of 3 machines and station 2 consists of 4

I NEED AN ANSWER QUICK! I WILL UPVOTE! I NEED AN ANSWER QUICK! I WILL UPVOTE! 2. A

2. A two-station line where station 1 consists of 3 machines and station 2 consists of 4 machines. Further, the line produces two different parts: 'A'parts and 'B'parts, with 40% of total parts produced being 'A's and 60% being 'B's. The average time to produce each partateach station is listed in the table. What is the bottleneck rate of this line? Station 1 (3 machines) Station 2 (4 machines) 'A'parts (40%) | 'B' parts (60%) Average part 2.6 min 1.0 min 3.8 min 0.6 min rb =