Question: I need an urgent answer, please! The company Maple & Nuts The company Maple and Nuts makes two types of products. The following is the

I need an urgent answer, please!

The company Maple & Nuts

The company Maple and Nuts makes two types of products. The following is the master production schedule for the Maple product, from which some information is missing.

Product

Initial inventory

Lot size

EU

Lead time

Maple

500

2

Week

7

8

9

10

11

12

13

14

15

16

Forecast

200

200

200

200

200

250

250

Customer orders

100

250

200

150

250

25

5

Projected on hand inventory

Available-to-promise

Planned order receipts

0

0

200

200

200

250

250

Planned order releases

200

200

200

250

250

Maple product.

1.1. Calculate, directly on the table, the on-hand inventory, and the available-to-promise.

1.2. What is the lot-sizing policy for the Maple product?

1.3. What is the production lead time?

1.4. Would it be possible to accept a new order for 100 units in week 15? Justify your answer.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!