Question: I need answer ASAP Solve the problem below using the intuitive least cost method and answer the following (Remember: Add the dummy, if unbalanced!): Cranbury
I need answer ASAP
Solve the problem below using the intuitive least cost method and answer the following (Remember: Add the dummy, if unbalanced!):
| Cranbury | Plainfield | Saddle Brook | Supply | |
| Gallway | $17 | $22 | $27 | 300 |
| Hendron | $23 | $21 | $19 | 250 |
| Vienna | $16 | $25 | $18 | 280 |
| Demand | 275 | 225 | 300 |
a. What is the maximum quantity that can be shipped from Gallway to Plainfield? [ Select ] ["270", "122", "225", "321"]
b. What is the maximum quantity that can be shipped from Vienna to Cranbury? [ Select ] ["100", "250", "$27", "275", "$16"]
c. What is the maximum quantity that can be shipped from Gallway to Saddlebrook? [ Select ] ["250", "$22", "0", "$27", "45"]
d. What will be the cost of this assignment? [ Select ] ["$14,975", "$23,500", "$14,425", "$12,290", "$15,405"]
e. Were all demand levels met? [ Select ] ["yes", "no", "cannot determine based on the information given"] If so/not, which site(s) was/were not? [ Select ] ["All demand levels were met", "Saddlebrook", "Plainfield and Saddlebrook", "Cranbury", "Plainfield"]
f. Was all supply exhausted? If so, which site(s) [ Select ] ["No, Hendron had 30 units remaining", "No, Gallway had 30 units remaining", "No, Gallway had 5 units remaining and so did Vienna with 25 units", "No, Vienna had 20 units remaining"]
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts