Question: i need answer in 30 min plz i will upvote asap thank u in advance Q4: A- The following table gives activities of durations of

i need answer in 30 min plz i will upvote asap thank u in advance i need answer in 30 min plz i will upvote asap
Q4: A- The following table gives activities of durations of construction project work: a. Draw the network for the project. b. Find the critical path. c. The free float time. d. The total float. Activity Predecessors Duration(days) A 30 B C A 15 D B,C 9 E A 18 F E,D 15 B- What are the benefits of PERT? 35

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!