Question: I need assistance in understanding how to solve this question Manatee Splash is going from strength to strength. Production is at 22,000/day. Daily demand is
I need assistance in understanding how to solve this question
Manatee Splash is going from strength to strength. Production is at 22,000/day. Daily demand is currently 20,000 units/day. It is forecast that daily demand will triple next year. Assume 8 hour days and 240 workdays per year.
How many bottling machines (total) should Jacee plan to own to meet this demand (round up to the nearest who number)?