Question: i need C the standard time A job was timed for 60 cycles and had an average of 119 minutes per piece. The performance rating

A job was timed for 60 cycles and had an average of 119 minutes per piece. The performance rating was 89 percent, and workday allowances are 14 percent. Determine each of the following a. Observed time (Round your onswer to 2 decimal ploces.) Answer is complete and correct. b. Normal time (Round your onswer to 2 decimal places.) b. Normal time. (Round your answer to 2 decimal places.) Answer is complete and correct. 1.06minutes c. Standard time. (Round your onswer to 2 decimol places.)