Question: I need fast help in this question. I have only 30 minutes. Please do them in excel and do it correctly 100%. QUESTION 1 10
I need fast help in this question. I have only 30 minutes. Please do them in excel and do it correctly 100%.

QUESTION 1 10 points Save Answer A series of dikes need to be built along a flood plain. Each dike is practically the same as far as difficulty, terrain, design, etc. The first dike takes 60 days to be built. If subsequent dikes are built at a 55.3105% learning curve rate, state below the time needed to produce the ninth dike (rounded to the closest hundredth of a day, e.g. 24.43 days). For the toolbar, press ALT+F10 (PC) or ALT+FN+F10 (Mac). B 1 U Paragraph Arial 10pt Tv % a === X2 X2 > TT ABC v T 15 X A EXE ;) #