Question: i need hell finding he projected ending inventories, net requirements, planned receipts, and order releases. thank you!! Consider the following master schedule record. Now suppose

i need hell finding he projected ending inventories, net requirements, planned receipts, and order releases. thank you!! i need hell finding he projected ending
i need hell finding he projected ending
Consider the following master schedule record. Now suppose the lead time for item A2 is three weeks rather than two weeks. Based on this information, can the company support the current gross requirements for the A2? What are the implications of having reliable supplier and manufacturing lead times in an MRP environment? e Click the icon to view the MRP record. Calculate the material requirements plan (enter your responses as whole numbers and include a minus sign if necessary). 1 2 4 3 300 5 250 Week ***A2" LT(weeks) = 3 6 200 100 50 0 30 220 190 0 0 0 Gross requirements Scheduled receipts Projected ending inventory: 290 Net requirements Planned receipts 0 0 80 50 250 200 0 80 250 Min. order = 1 50 200 mter your answer in the edit fields and then click Check Answer. parts - remaining Clear All Check Answer Problem 7 Question Help Consider the following master schedule record. Now suppose the lead time for item A2 is three weeks rather than two weeks. Basec on th ble sup: * More Info More Info Sald 1 2 6 Week ***A2*** LT(weeks) = 2 3 300 4 50 5 250 100 200 0 30 Gross requirements Scheduled receipts Projected ending inventory: 290 Net requirements Planned receipts Planned orders Min. order = 1 Print Done el your answer ITO SOTU TOTUS aru METTETICROTOCK ANSWER parts remaining Clear All Check

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!