Question: I need help constructing a network schedule for the stadium project Ventura Baseball Stadium Case The G&E Company is preparing a bid to build the
I need help constructing a network schedule for the stadium project
Ventura Baseball Stadium Case
The G&E Company is preparing a bid to build the new 47,000-seat Ventura baseball stadium. The construction must start on June 10, 2019, and be completed in time for the start of the 2022 season. A penalty clause of $500,000 per day of delay beyond April 3rd is written into the contract.
Will the project be able to be completed by the April 3rd deadline? How long will it take
What is the critical path for the project?
Based on the schedule would you recommend that G&E pursue this contract? Why? Include a one-page Gantt chart for the stadium schedule.