Question: I need help finding the answer for this problem Look at Project TX55: LS(N)=128,LS(P)=113, and LS(Q)=132 The duration of activities D, E, and F are

I need help finding the answer for this problem
I need help finding the answer for this problem
I need help finding the answer for this problem
Look at Project TX55: LS(N)=128,LS(P)=113, and LS(Q)=132 The duration of activities D, E, and F are 29, 26, and 27 days, respectively. The duration of activities G,H,K, and M are 18,15,26, and 33 days, respectively Find LS(D)