An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EFB=15,EFC=17,LFB=24,LFC=27; activity times are A=4,B=6, C=8 Select one: a. 14 b. 15 c. 16 d. 17 e. 18 A Gantt chart can be a useful tool for simple projects. Select one: True False