Question: i need help i got 1.44 but it says that it was wrong Additional Algo 4-8 Add one worker People are served in a process
Additional Algo 4-8 Add one worker People are served in a process with two resources. The first resource has a capacity of 1.4 people per minute. The capacity of the second resource is 1.2 people per minute. The first resource has 3 workers and the second resource has 5 workers, One additional worker is hired who is as productive as the current workers. What is the new capacity of this process? Note: Do not round intermediate calculations. Round your answer to 3 decimal places