Question: I need help sloving to find the answer? Look at the network diagram CPM-4. The duration of activity D, E, and F are 68,70 ,
I need help sloving to find the answer?
Look at the network diagram CPM-4. The duration of activity D, E, and F are 68,70 , and 73 days, respectively. The duration of activity G,H, and K are 16,32 , and 41 days, respectively. Furthermore EF(G)=155,EF(H)=147, and EF(K)=143. Find the value of LF(B). P.W. Sutanto

Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
