Question: I need help solving this problem Prepare a master production schedule for industrial pumps in the manner of the following table. Use the MPS rule
Prepare a master production schedule for industrial pumps in the manner of the following table. Use the MPS rule to "schedule production when the projected on-hand inventory would be less than 10 without production." Suppose that there are curfently 64 pumps in inventory and a production lot size of 70 pumps is used. (Leave no cells blank-be certain to enter "0" wherever required.)