Question: I need help understanding the question, dont really understand the CPM diagram (a) 11 days (b) 12 days (c) 13 days (d) 15 days (e)
I need help understanding the question, dont really understand the CPM diagram 
(a) 11 days (b) 12 days (c) 13 days (d) 15 days (e) 17 days (f) no answers are correct
Consider the attached CPM diagram. Units are in days. Find the project completion time. D 4 A F 2 5 2 E 1 5 6 7 G 3 B 6 3 6 Select an answer and submit. For keyboard navigation, use the up/down arrow keys to select anStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts