Question: I need help understanding the question, dont really understand the CPM diagram (a) 11 days (b) 12 days (c) 13 days (d) 15 days (e)

I need help understanding the question, dont really understand the CPM diagram I need help understanding the question, dont

(a) 11 days (b) 12 days (c) 13 days (d) 15 days (e) 17 days (f) no answers are correct

Consider the attached CPM diagram. Units are in days. Find the project completion time. D 4 A F 2 5 2 E 1 5 6 7 G 3 B 6 3 6 Select an answer and submit. For keyboard navigation, use the up/down arrow keys to select an