Question: I need help with the excel formulas for part 3 Product ( A ) is an end item and is made from one units of

I need help with the excel formulas for part 3 Product \\(

I need help with the excel formulas for part 3

Product \\( A \\) is an end item and is made from one units of \\( B \\), and \\( C \\). B is made from one unit of C and two units of D.C is made from one unit of \\( D \\). A has a lead time of one week. \\( B \\) and \\( C \\) have lead times of two weeks. and \\( D \\) have lead times of one week