Question: I need help with this assignment. I have followed all of the instructions for this assignment and simply do not understand why I am unable

I need help with this assignment. I have followed all of the instructions for this assignment and simply do not understand why I am unable to duplicate the same results as the Chegg Expert.

I have attached (3) screenshots in all. The first (2) are my results and the last one is the Chegg Experts results. & Lastly, I have included the project details for how I built my Gantt Chart and Network Diagram because I don't know who will get this question which please tell me what I am not doing correctly, or please confirm that I am doing it correctly. I do not have confidence in my results because they differ from that of the Chegg Expert.

I tried leaving a comment on the help I received this morning and have been patiently waiting for a reply to no avail... I am quickly running out of time to turn in my assignment which is due by 11:59 pm on 12/18/2020. I am unable to complete the rest of my assignment which entails writing a paper with regard to the answers to the project details. So, this is a major component of my assignment. Please help!!!!

(My Gantt Chart Results)

I need help with this assignment. I have followed

(My Network Diagram reflecting the Critical Path Results)

I need help with this assignment. I have followed

(Answer provided by Chegg Expert)

I need help with this assignment. I have followed

(Case Details to develop the Gantt Chart and Network Diagram)

Updated Case 6.2: Montview Stadium Case

The G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball stadium. The construction must start on July 1, 2020, and be completed in time for the start of the 2024 season. A penalty clause of $100,000 per day of delay beyond April 3 is written into the contract.

Percival Young, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $3 million on the project. He also said if they were successful, the prospects of future projects are bright since there is a projected renaissance in building classic ballparks with modern luxury boxes.

Assignment

Given the information provided in Table 1, construct a network schedule for the stadium project and answer the following questions:

1. Will the project be able to be completed by the April 3rd deadline? How long will it take? How many working days are projected?

2. What is the critical path for the project? List the activities on the critical path.

3. Based on the schedule would you recommend that G&E pursue this contract? Why or why not?

Technical Details for the Shoreline Baseball Stadium

For the purposes of this case assume the following:

  1. The following holidays are observed: January 1, Martin Luther King Day (third Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.
  2. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.
  3. The crews work standard days, Monday through Friday.

Table 1: Montview Baseball Stadium Case

ID

Activity

Duration (days)

Predecessor(s)

1

Clear stadium site

75

-

2

Demolish present stadium

40

1

3

Establish construction site

70

2

4

Drive support piling

110

3

5

Install lower bowl

125

4

6

Install main concourse

110

5

7

Install playing field

95

5

8

Construct upper steel bowl

110

5

9

Install seats

160

8

10

Build luxury boxes

90

8

11

Install Jumbotron

25

8

12

Install infrastructure

110

8

13

Build steel canopy

80

9

14

Install lighting

25

9

15

Construct roof supports

90

3

16

Build roof

150

15

17

Construct roof racks

90

13

18

Install roof supports

90

16,17

19

Final inspection

25

7,10,12,14,18

File Task Resource Report Project View Help Format Tell me what you want to do ABC Spelling Proofing 2021 MM Half 2.2021 Hal 209 1 M 2 2033 Hal 2002 s H2033 M Hai 130 M N) N N M M N PIRIT Status Date: NA Et Get Add-in O El Update Project Subproject Project Custom Links Between WBS My Add-ins - Change Calculate Set Move Information Fields Projects Working Time Project Baseline - Project Insert Add-ins Properties Schedule Status Tack Total H 22000 Made T Task Name Duratio- Duration - Start Finish - Predecessors 5 0 Updated Case 6.2 975 days 1670 days Wed 7/1/20 Fri 4/5/24 Montview Stadium Case_Rough draft 2 1 Clear stadium site 75 days 75 days Wed 7/1/20 Tue 10/13/20 2 Demolish present stadium 40 days 40 days Wed 10/14/20 Tue 12/8/201 Establish construction site 70 days 70 days Wed 12/9/20 Thu 3/18/21 2 4 Drive support piling 110 days 110 days Fri 3/19/21 Mon 8/23/21 3 5 Install lower bowl 125 days 125 days Tue 8/24/21 Fri 2/18/224 6 Install main concourse 110 day : 110 days Mon 2/21/22 Fri 7/22/22 5 Install playing field 95 days 95 day Mon 2/21/22 Fri 7/1/22 5 8 Construct upper steel 110 days 110 days Mon 2/21/22 Fri 7/22/22 5 bowl Intall seats 160 days 160 days Mon 7/25/22 Fri 3/3/23 8 Build luxury boxes 90 days 90 days Mon 7/25/22 Fri 11/25/22 8 Install Jumbotron 25 days 25 days Mon 7/25/22 Fri 8/26/22 8 12 Install infrastructure 110 days 110 days Mon 7/25/22 Fri 12/23/22 8 13 Build steel canopy 80 days 80 days Mon 3/6/23 Fri 6/23/23 9 14 Install lighting 25 days 25 days Mon 3/6/23 Fri 4/7/23 9 15 Construct roof supports 90 days 90 days Fri 3/19/21 Mon 7/26/21 3 16 Build roof 150 days 150 days Tue 7/27/21 Fri 2/25/22 15 17 Construct roof racks 90 days 90 days Mon 6/26/23 Fri 10/27/23 13 Install roof supports 90 days 90 days Mon 10/30/23 Fri 3/1/24 16,17 19 Final inspection 25 days 25 days Mon 3/4/24 Fri 4/5/24 7,10,12,14,18 GANTT CHART IIIIIIIIIII File Task Resource Report Project View Help Format Tell me what you want to do + Timescale: Timeline 21 Switch Windows Arrange All Details Network Diagram Calendar - Gantt Task Chart- Usage - Other Views Task Views Resource Usage - Team Resource Sheet Planners Other Views Resource Views Sort Outline Tables - Highlight [No Highlighti- Filter INo Filter Group by: INo Group) Data New Macros Zoom Ente Sected - Project The Zoom Window Hide Split View Window Macros 1) According to the activities necessary to complete the Shoreline Baseball Stadium project, the Gantt chart is: 75 Montview Baseball Stadium 375 days Wed 7/1/20 Mon 5/6/24 Clear stadium Wed 11/20 Thu 10/15/20 Demolish present stumdays in 30/10/2012/11/201 Establish construction site 70 days Mon 12/14/20 Wed 134/212 Driveport piling 110 days Ta 18/11 1/27/21 lower bowl 125 days Mon/30/21 Mon 2/20/214 main concours 110 days Tue 1/1/22 Wed 11/22 playing field 5 days Tue 1/1/22 Wed 7/11/25 Construct upper steel bowl 110 days Tue 11/22 Wed 11/22 100 days u 1/4 l Wed 1/22/23 Build luxury bones 8 day thua 4/4 112/9/22 # lumbotron 25 Tin l Hu/ . Install infrastructure 110 days Thua 1/4 l Tue 1/10/23 del cano 30 days The 1/21/22 7/4/23 3 23 days Thu H Wed 4/21/239 Constroof supports days The 20/21 7/30/22 Build roof 150 days Mon 12/21 Mon 11/22 15 Contrast roof racks days Mon 7/11/23 Mon 11/20/23 13 install roof supports days Tue 11/21/23 Mon 4/1/24 16.17 Final inspection 25 days Tow/2/24 Mon/ 7.10.12,14,10 11 14 35 1 The project would take 975 working days for development, considering holidays. If the start date is July 1st, 2020, the end date would be May 6th, 2024. Therefore, the project is unlikely to be completed by April 3rd, 2024. 2) The Network Diagram of the project and the critical path are: The activities in the critical path are (highlighted in red): File Task Resource Report Project View Help Format Tell me what you want to do ABC Spelling Proofing 2021 MM Half 2.2021 Hal 209 1 M 2 2033 Hal 2002 s H2033 M Hai 130 M N) N N M M N PIRIT Status Date: NA Et Get Add-in O El Update Project Subproject Project Custom Links Between WBS My Add-ins - Change Calculate Set Move Information Fields Projects Working Time Project Baseline - Project Insert Add-ins Properties Schedule Status Tack Total H 22000 Made T Task Name Duratio- Duration - Start Finish - Predecessors 5 0 Updated Case 6.2 975 days 1670 days Wed 7/1/20 Fri 4/5/24 Montview Stadium Case_Rough draft 2 1 Clear stadium site 75 days 75 days Wed 7/1/20 Tue 10/13/20 2 Demolish present stadium 40 days 40 days Wed 10/14/20 Tue 12/8/201 Establish construction site 70 days 70 days Wed 12/9/20 Thu 3/18/21 2 4 Drive support piling 110 days 110 days Fri 3/19/21 Mon 8/23/21 3 5 Install lower bowl 125 days 125 days Tue 8/24/21 Fri 2/18/224 6 Install main concourse 110 day : 110 days Mon 2/21/22 Fri 7/22/22 5 Install playing field 95 days 95 day Mon 2/21/22 Fri 7/1/22 5 8 Construct upper steel 110 days 110 days Mon 2/21/22 Fri 7/22/22 5 bowl Intall seats 160 days 160 days Mon 7/25/22 Fri 3/3/23 8 Build luxury boxes 90 days 90 days Mon 7/25/22 Fri 11/25/22 8 Install Jumbotron 25 days 25 days Mon 7/25/22 Fri 8/26/22 8 12 Install infrastructure 110 days 110 days Mon 7/25/22 Fri 12/23/22 8 13 Build steel canopy 80 days 80 days Mon 3/6/23 Fri 6/23/23 9 14 Install lighting 25 days 25 days Mon 3/6/23 Fri 4/7/23 9 15 Construct roof supports 90 days 90 days Fri 3/19/21 Mon 7/26/21 3 16 Build roof 150 days 150 days Tue 7/27/21 Fri 2/25/22 15 17 Construct roof racks 90 days 90 days Mon 6/26/23 Fri 10/27/23 13 Install roof supports 90 days 90 days Mon 10/30/23 Fri 3/1/24 16,17 19 Final inspection 25 days 25 days Mon 3/4/24 Fri 4/5/24 7,10,12,14,18 GANTT CHART IIIIIIIIIII File Task Resource Report Project View Help Format Tell me what you want to do + Timescale: Timeline 21 Switch Windows Arrange All Details Network Diagram Calendar - Gantt Task Chart- Usage - Other Views Task Views Resource Usage - Team Resource Sheet Planners Other Views Resource Views Sort Outline Tables - Highlight [No Highlighti- Filter INo Filter Group by: INo Group) Data New Macros Zoom Ente Sected - Project The Zoom Window Hide Split View Window Macros 1) According to the activities necessary to complete the Shoreline Baseball Stadium project, the Gantt chart is: 75 Montview Baseball Stadium 375 days Wed 7/1/20 Mon 5/6/24 Clear stadium Wed 11/20 Thu 10/15/20 Demolish present stumdays in 30/10/2012/11/201 Establish construction site 70 days Mon 12/14/20 Wed 134/212 Driveport piling 110 days Ta 18/11 1/27/21 lower bowl 125 days Mon/30/21 Mon 2/20/214 main concours 110 days Tue 1/1/22 Wed 11/22 playing field 5 days Tue 1/1/22 Wed 7/11/25 Construct upper steel bowl 110 days Tue 11/22 Wed 11/22 100 days u 1/4 l Wed 1/22/23 Build luxury bones 8 day thua 4/4 112/9/22 # lumbotron 25 Tin l Hu/ . Install infrastructure 110 days Thua 1/4 l Tue 1/10/23 del cano 30 days The 1/21/22 7/4/23 3 23 days Thu H Wed 4/21/239 Constroof supports days The 20/21 7/30/22 Build roof 150 days Mon 12/21 Mon 11/22 15 Contrast roof racks days Mon 7/11/23 Mon 11/20/23 13 install roof supports days Tue 11/21/23 Mon 4/1/24 16.17 Final inspection 25 days Tow/2/24 Mon/ 7.10.12,14,10 11 14 35 1 The project would take 975 working days for development, considering holidays. If the start date is July 1st, 2020, the end date would be May 6th, 2024. Therefore, the project is unlikely to be completed by April 3rd, 2024. 2) The Network Diagram of the project and the critical path are: The activities in the critical path are (highlighted in red)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!