Question: I need help with this plz Question 6 Question 7 Question 8 This exercise conlains only parts d,b, and c. d) Using the line drawing

I need help with this plz
Question 6 Question 7 Question 8 This exercise conlains only parts d,b, and c. d) Using the line drawing tool five times, draw a Gantt chart for activities C through G of the project based on the early times. Question 9 Carefully follow the instructions above, and only draw the required objects. b) The critical path activities for the leadership training program development project are Question 10 c) The expected project completion time for the leadership training program development project = hours (round your response to one decimal place). Question 11 Question 12 Question 13