Question: I NEED IT ASAP, PLEASE HELP USED ONLY 2 DECIMAL. BOX THE FINAL ANSWERS. SOLUTION MUST BE COMPLETE (GIVE, WHAT IS BEING ASKED, FORMULA, SOLUTIONS,

I NEED IT ASAP, PLEASE HELP

USED ONLY 2 DECIMAL. BOX THE FINAL ANSWERS.

SOLUTION MUST BE COMPLETE (GIVE, WHAT IS BEING ASKED, FORMULA, SOLUTIONS, ANSWER)

A contract is awarded for P100,000. It is to be completed in 4 weeks' time, subject to a penalty of P2400 per day if the time is exceeded. At the end of three weeks, the work is 60% complete. Cost of labor was initially estimated at P40000 when working 40 hours per week. If overtime labor must be compensated at double time and work is 8 hours a day straight time, on the revised work schedule determine: (a) Which would be cheaper, to take the penalty or to complete the job by working overtime? (b) By what percent would the labor cost be reduced by the cheaper plan?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Economics Questions!