Question: i need problem D solved. View previous attempt Check my work 3 IMMEDIATE ACTIVITY PREDECESSORS A D c A 15 points TINES DAYS D. 1
i need problem D solved.
View previous attempt Check my work 3 IMMEDIATE ACTIVITY PREDECESSORS A D c A 15 points TINES DAYS D. 1 1 4 4 5 3 7 11 1 2 1 6 1 2 12 2 3 10 2 3 10 C, D. F. 00:43:53 b. What is the critical path? Print O AC-F.H A-D-G-H O ADF.H 88 E-G-H c. What is the expected project completion time? (Round your answer to 3 decimal places.) Project completion time 185 days d. What is the probability of completing this project within 19 days? (Do not round Intermediate calculations. Round your answer to 4 decimal places.)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock