Question: I need the answer as soon as possible UV Ltd. presents the following information for November, 2013: Budgeted production of product P = 200 units.

I need the answer as soon as possible I need the answer as soon as possible UV Ltd.

UV Ltd. presents the following information for November, 2013: Budgeted production of product P = 200 units. Standard consumption of Raw materials = 2 kg. per unit of P. Standard price of material A = 6 per kg. Actually, 250 units of P were produced and material A was purchased at 8 per kg and consumed at 1.8 kg per unit of P. Calculate the Material Cost Variances