Question: i need the answer typed Q.2. The standard time and standard rate of labor to produce Product P are as follows: Standard Time: 80 hrs

 i need the answer typed Q.2. The standard time and standard

i need the answer typed

Q.2. The standard time and standard rate of labor to produce Product P are as follows: Standard Time: 80 hrs Actual Time: 90 hrs Standard Rate: AED 40/hr Actual Rate: AED 44/hr Idle Time - 4 hours Calculate: a. Labour Cost Variance c. Labour Efficiency Variance b. Labour Rate Variance d.ldle Time Variance

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!