Question: I need the slack determined, I keep getting it wrong. Dave Fletcher was able to determine the activity times for constructing his laser scanning machine.
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activily. The total project completion fime and the critical path should also be determined. Here are the activity times Dave's earliest stant (ES) and earliest finish (EF) are