Question: I need the solution within an hour please. Develop the LSM diagram for the following project and calculate the minimum total project duration, completing the

I need the solution within an hour please.
Develop the LSM diagram for the following project and calculate the minimum total project
duration, completing the below table.
The total length of pipe to be laid is 1,500ft. The contractor would like to keep a 1-day minimum
buffer between crews (e.g., the minimum buffer between Excavation and Laying Subbase is 1-
day). Please note that for some activities, the rate of progress changes halfway. Activity sequence
is: Excavation rarr Laying Subbase rarr Laying Pipe rarr Backfilling rarr Asphalt Base Course.
I need the solution within an hour please.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!