Question: I need to fill out the current chart, I also would need to see the formulas in excel of how each cell was determined. 1
I need to fill out the current chart, I also would need to see the formulas in excel of how each cell was determined.
1 B D E F G H Prepare a master schedule using the table displayed below. The MPS rule is to schedule production 2 if the projected on-hand inventory would be negative without it. Production lot size is 75 units. In 3 addition, determine the Available -to-Promise (ATP) quantity for each period. 600 w 4 5 6 7 8 9 10 11 12 13 14 15 On Hand 1 4 5 2 50 35 50 52 3 50 20 50 50 12 60 20 16 Forecast 17 Orders 18 Projected available balance 19 Available to Promise (ATP) 20 Master production Schedule 21 Lot size =75 22 23