Question: I need Utilization, Process CapacityMin, Flow Rate, MIN(Demand Capacity), Flow Rate, MIN(Demand Capacity), Cycle TIme (1/flow rate). Station Processing time # of workers and machines

I need Utilization, Process CapacityMin, Flow Rate, MIN(Demand Capacity), Flow Rate, MIN(Demand Capacity), Cycle TIme (1/flow rate).
Station Processing time # of workers and machines Raw Material Distribution 8 seconds 1 worker 1/8 0.125 car/sec 5.6 cars/min NO Car Body Production Tire Production Car Assembly 14 seconds 25 seconds 11 seconds 1 worker 1 worker 1 worker 1/14 1/25 1/11 0.07 car/sec 0.04 car/sec 0.09 cars/sec 4.2 cars/min 2.4 cars/min 5.4 cars/min NO YES NO Step Capacity 1/ Processing time Bottleneck? Utilization Process CapacityMIN(Step Capacity) Flow Rate MIN(Demand Capacity) Cycle Time (1/fFlow Rate)Step by Step Solution