Question: I only need help with question 6, question 5 is there for context. I already have one network (project planning?) diagram drawn out for the
I only need help with question 6, question 5 is there for context. I already have one network (project planning?) diagram drawn out for the table that is pictured. I just need help with the drawing for question 6.
5) Next, your boss would like you to study the impact of making two changes to how the project structure is organized. The first change involves the following.
a) Using dedicated teams that would work strictly in parallel on the activities in each subproject. For example, in subproject P (product specifications) the team would work on P1, P2, P3, and P4 all in parallel. In other words, there would be no precedence relationships within a subprojectall tasks within a subproject would be worked on at the same time and each would take the same amount of time as originally specified.
b) with this new design, all the subprojects would be done sequentially with P done first, then S, D, I, and finally V.
How long would it take to complete the project if this change were made? What would be the expected impact when this new completion time is compared with the original completion time? [Provide single-sentence answers to both questions.]
The second change your boss would like you to consider would be to select the suppliers during subproject P and have them work directly with the dedicated teams as described in step 5. This would involve adding an activity to subproject P called P5; Activity P5 will encompass supplier selection and contract negotiation and will have a duration of 12 weeks. This new activity would be done in parallel with P1, P2, P3, and P4. Because of this change, subprojects S and V would be eliminated from the project. How long would it take to complete the project now if this additional change were made? What would be the expected impact of this change on the project? [Provide single-sentence answers to both questions.] (4 points)
(6) Draw the revised network diagram after making all the changes in Q5. [So, in total there will be no more than two network diagrams in your submitted report.] (6 points)

Q1) Data is provided in Table 1. Show the network diagram on the next page. Q2) The project will take weeks to complete. The critical path is Q3 and Q4) Enter answers for both questions in Table 1 below. Table 1: WBS for the Cell Phone Design Project