Sanchez Company's output for the current period was assigned a $413,000 standard direct labor cost. The direct labor variances included a $10,325 unfavorable direct labor rate variance and a $4,130 favorable direct labor efficiency variance. What is the actual total direct labor cost for the current period?
Multiple Choice
$427,455.
$398,545.
$406,805.
$419,195.
$423,325.