Question: Ice Bear Corporation's management reports that its average delivery cycle time is 30 days, its average throughput time is 10.0 days. Its manufacturing cycle efficiency

Ice Bear Corporation's management reports that its average delivery cycle time is 30 days, its average throughput time is 10.0 days. Its manufacturing cycle efficiency (MCE) is 0.42 Its average move time is 0.4 day, and its average queue time is 4.0 days. Required: a. What is the wait time? (Round your answer to 1 decimal place.) b. What is the process time? (Round your answer to 1 decimal place.) c. What is the inspection time? (Round your intermediate calculations and final answer to 1 decimal place.) a. Wait time b. Process time c. Inspection time days days days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
