Question: ID# Activity Name Estimated Duration (in work hours) Resource (persons name or job title) Predecessor (dependency) 0 Recreation and Wellness Internet Project Tony Prince 1.0
| ID# | Activity Name | Estimated Duration (in work hours) | Resource (persons name or job title) | Predecessor (dependency) |
| 0 | Recreation and Wellness Internet Project |
| Tony Prince |
|
| 1.0 | Project Management | 85 | Tony Prince |
|
| 2.0 | Requirements Definition | 85 | Nancy | 1.0 |
| 3.0 | Web site design | 160 | Kane | 2.0 |
| 3.1 | Registration for recreational programs | 80 | Nancy | 2.0 |
| 3.2 | Registration for classes and programs | 80 | Nancy | 2.0 |
| 3.3 | Tracking systems | 85 | Kane | 2.0 |
| 3.4 | Incentive systems | 160 | Nancy | 2.0 |
| 4.0 | Web site development | 330 | George | 3.0 |
| 4.1 | Registration for recreational programs | 85 | Nancy | 3.1 |
| 4.2 | Registration for classes and programs | 85 | Nancy | 3.2 |
| 4.3 | Tracking systems | 85 | Patrick | 3.3 |
| 4.4 | Incentive systems | 85 | Tony Prince | 3.4 |
| 5.0 | Testing | 40 | George/Bonnie/Patrick | 4.4 |
| 6.0 | Training, rollout, and support | 160 | George | 5.0 |
|
|
|
|
|
|
|
| Total Project Time | 1040 |
|
|
Above is the Activities List with Estimated Durations and Resource Needs. Using the data included in this document, create a project schedule using Microsoft Project 2013 or 2016. Attach your Microsoft Project Schedule file to this assignment.