Question: ID# Activity Name Estimated Duration (in work hours) Resource (persons name or job title) Predecessor (dependency) 0 Recreation and Wellness Internet Project Tony Prince 1.0

ID#

Activity Name

Estimated Duration (in work hours)

Resource (persons name or job title)

Predecessor (dependency)

0

Recreation and Wellness Internet Project

Tony Prince

1.0

Project Management

85

Tony Prince

2.0

Requirements Definition

85

Nancy

1.0

3.0

Web site design

160

Kane

2.0

3.1

Registration for recreational programs

80

Nancy

2.0

3.2

Registration for classes and programs

80

Nancy

2.0

3.3

Tracking systems

85

Kane

2.0

3.4

Incentive systems

160

Nancy

2.0

4.0

Web site development

330

George

3.0

4.1

Registration for recreational programs

85

Nancy

3.1

4.2

Registration for classes and programs

85

Nancy

3.2

4.3

Tracking systems

85

Patrick

3.3

4.4

Incentive systems

85

Tony Prince

3.4

5.0

Testing

40

George/Bonnie/Patrick

4.4

6.0

Training, rollout, and support

160

George

5.0

Total Project Time

1040

Above is the Activities List with Estimated Durations and Resource Needs. Using the data included in this document, create a project schedule using Microsoft Project 2013 or 2016. Attach your Microsoft Project Schedule file to this assignment.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!