Question: ID Description Predecessor Duration ( Days ) Slack ( SL ) A Survey - 5 0 B Soils report A 2 0 2 5 C

ID
Description
Predecessor Duration (Days) Slack
(SL)
A Survey -50
B Soils report A 2025
C Traffic design A 300
D Parking Lot Layout A 50
E Approve Design B, C, D 800
F Lighting E 150
G Drainage E 300
H Landscape E 250
I Signage E 150
J Bid Proposal F, G, H, I 100