+ ID Page view | A Read aloud | DR 6) a) Create new Network Diagram and b) Calculate new critical path and slack times. Predecessors Weeks 4 Activity 1 2 3 4. 5 6 7. 8 9 10 11 Immediate Activity Collect requirements Analyze processes Analyze data Design processes Design data Design screens Design reports Program Test and document Install Maintain 6 21 12 2 15 8 16 4 1 1 2 2 2 3,4 4,5 6,7 7 8,9 9, 10