Question: ID PERT 2 Using PERT Julie was able to determine that the expected project completion time for the construction of a pleasure yacht is 2

ID PERT2
Using PERT Julie was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months and the project variance is 4. What is the due date that yields a 95% of completion?
24.29
21.84
27.34
22.53

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock