Question: ID Risk Event Likelihood Severity A Project requires new technology and support structure Medium Low B Web infrastructure lacks sufficient transaction capacity Medium High C

ID Risk Event Likelihood Severity
A Project requires new technology and support structure Medium Low
B Web infrastructure lacks sufficient transaction capacity Medium High
C IS resources are spread too thin High High
D The intranet site suffers a security breach Low High

Figure 10-1 Excerpt from Internet Project Risk Register Consider the excerpt of the Internet Project risk register presented in Figure 10-1. Which of the following risk events should receive the highest priority for the development of risk responses?

a. B - web infrastructure lacks sufficient transaction capacity
b. D - The intranet site suffers a security breach
c. C - IS resources are spread too thin
d. A - project requires new technology and support structure

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!