Question: ID Task Name % Complete Duration Work Start Finish Predecessors Resource Names Cost Baseline Start Baseline Finish CV SV ACWP BCWP BCWS Baseline Cost EAC

IDTask Name% CompleteDurationWorkStartFinishPredecessorsResource NamesCostBaseline StartBaseline FinishCVSVACWPBCWPBCWSBaseline CostEACNotes
1Wellness Vendor Project24%232 days3,238.8 hrsTue 2/14/17Sun 12/31/17$234,124.00Tue 2/14/17Sun 12/31/17$0.00($4,680.00)$0.00$0.00$4,680.00$234,124.00$234,124.00
2 Initiation89%24 days80 hrsThu 5/4/17Tue 6/6/17$7,680.00Thu 5/4/17Tue 6/6/17$0.00$0.00$0.00$0.00$0.00$7,680.00$7,680.00
3 Budget dollar service request100%5 days40 hrsThu 5/4/17Wed 5/10/17IS Manager$3,800.00Thu 5/4/17Wed 5/10/17$0.00$0.00$0.00$0.00$0.00$3,800.00$3,800.00
4 Project Charter75%2 days16 hrsSat 6/3/17Tue 6/6/17Business Owner$1,600.00Sat 6/3/17Tue 6/6/17$0.00$0.00$0.00$0.00$0.00$1,600.00$1,600.00
5 Obtain Approvals80%3 days24 hrsFri 6/2/17Tue 6/6/17IS Manager$2,280.00Fri 6/2/17Tue 6/6/17$0.00$0.00$0.00$0.00$0.00$2,280.00$2,280.00
6 Planning87%41 days144 hrsSun 6/11/17Mon 8/7/17$10,440.00Sun 6/11/17Mon 8/7/17$0.00$0.00$0.00$0.00$0.00$10,440.00$10,440.00
7 Project Plan100%8 days64 hrsSat 7/15/17Fri 8/4/17Project Manager$4,800.00Sat 7/15/17Fri 8/4/17$0.00$0.00$0.00$0.00$0.00$4,800.00$4,800.00
8 Resource allocation approvals75%4 days32 hrsSun 6/11/17Mon 8/7/177Project Manager$2,400.00Sun 6/11/17Mon 8/7/17$0.00$0.00$0.00$0.00$0.00$2,400.00$2,400.00
9 Communication67%3 days48 hrsSat 7/29/17Wed 8/2/17$3,240.00Sat 7/29/17Wed 8/2/17$0.00$0.00$0.00$0.00$0.00$3,240.00$3,240.00
10 Develop Communication Plan100%0 days0 hrsSat 7/29/17Sat 7/29/17Project Manager$0.00Sat 7/29/17Sat 7/29/17$0.00$0.00$0.00$0.00$0.00$0.00$0.00
11 Review/Approve Communication Plan67%3 days48 hrsMon 7/31/17Wed 8/2/1710Project Manager,SME$3,240.00Mon 7/31/17Wed 8/2/17$0.00$0.00$0.00$0.00$0.00$3,240.00$3,240.00
12 Project Kickoff100%1 day8 hrsFri 5/5/17Fri 5/5/17All stakeholders$10.00Fri 5/5/17Fri 5/5/17$0.00$0.00$0.00$0.00$0.00$10.00$10.00
13 Execution34%119 days2,771.6 hrsThu 7/13/17Fri 12/22/17$197,324.00Thu 7/13/17Fri 12/22/17$0.00$0.00$0.00$0.00$0.00$197,324.00$197,324.00
14 Vendor Wellness DB Tables98%55 days424 hrsThu 8/10/17Tue 10/24/17$35,685.00Thu 8/10/17Tue 10/24/17$0.00$0.00$0.00$0.00$0.00$35,685.00$35,685.00
15 Create Tables100%48 days368 hrsThu 8/10/17Fri 10/13/17$32,525.00Thu 8/10/17Fri 10/13/17$0.00$0.00$0.00$0.00$0.00$32,525.00$32,525.00
16 Create/Modify vendor database tables100%41 days320 hrsThu 8/10/17Wed 10/4/17DBA1$28,810.00Thu 8/10/17Wed 10/4/17$0.00$0.00$0.00$0.00$0.00$28,810.00$28,810.00
17 Promote tables to QA100%2 days16 hrsThu 10/12/17Fri 10/13/1716DBA1$1,450.00Thu 10/12/17Fri 10/13/17$0.00$0.00$0.00$0.00$0.00$1,450.00$1,450.00
18 Validate tables100%2 days16 hrsThu 10/5/17Fri 10/6/1717DBA1$1,450.00Thu 10/5/17Fri 10/6/17$0.00$0.00$0.00$0.00$0.00$1,450.00$1,450.00
19 UAT100%2 days16 hrsThu 10/5/17Fri 10/6/1718Business Analyst$815.00Thu 10/5/17Fri 10/6/17$0.00$0.00$0.00$0.00$0.00$815.00$815.00
20 Promote Tables to Production86%27 days56 hrsSat 9/16/17Tue 10/24/17$3,160.00Sat 9/16/17Tue 10/24/17$0.00$0.00$0.00$0.00$0.00$3,160.00$3,160.00
21 Create production ticket SR#100%3 days24 hrsSat 9/16/17Wed 9/20/17Business Analyst$1,215.00Sat 9/16/17Wed 9/20/17$0.00$0.00$0.00$0.00$0.00$1,215.00$1,215.00
22 Deploy Tables100%1 day8 hrsThu 10/19/17Thu 10/19/17DBA1$730.00Thu 10/19/17Thu 10/19/17$0.00$0.00$0.00$0.00$0.00$730.00$730.00
23 Validate Tables67%3 days24 hrsFri 10/20/17Tue 10/24/1722Business Analyst$1,215.00Fri 10/20/17Tue 10/24/17$0.00$0.00$0.00$0.00$0.00$1,215.00$1,215.00
24 Final Code Review-Module 1100%27 days120 hrsThu 9/7/17Fri 10/13/17$9,215.00Thu 9/7/17Fri 10/13/17$0.00$0.00$0.00$0.00$0.00$9,215.00$9,215.00
25 Module 1 code review100%21 days80 hrsThu 9/7/17Thu 10/5/17Developer$7,200.00Thu 9/7/17Thu 10/5/17$0.00$0.00$0.00$0.00$0.00$7,200.00$7,200.00
26 Validate data accuracy100%5 days40 hrsMon 10/9/17Fri 10/13/17Business Analyst$2,015.00Mon 10/9/17Fri 10/13/17$0.00$0.00$0.00$0.00$0.00$2,015.00$2,015.00
27 Final Code Review-Module 2100%26 days115.6 hrsThu 9/7/17Thu 10/12/17$9,139.00Thu 9/7/17Thu 10/12/17$0.00$0.00$0.00$0.00$0.00$9,139.00$9,139.00
28 Module 2 code review100%21 days83.6 hrsThu 9/7/17Thu 10/5/17Developer$7,524.00Thu 9/7/17Thu 10/5/17$0.00$0.00$0.00$0.00$0.00$7,524.00$7,524.00
29 Validate data accuracy100%4 days32 hrsMon 10/9/17Thu 10/12/1728Business Analyst$1,615.00Mon 10/9/17Thu 10/12/17$0.00$0.00$0.00$0.00$0.00$1,615.00$1,615.00
30 Final Code Review-Module 30%33 days128 hrsThu 10/5/17Fri 11/17/17$1,625.00Thu 10/5/17Fri 11/17/17$0.00$0.00$0.00$0.00$0.00$1,625.00$1,625.00Project BEHIND
31 Module 3 code review0%12 days96 hrsThu 10/5/17Fri 10/20/17All stakeholders$10.00Thu 10/5/17Fri 10/20/17$0.00$0.00$0.00$0.00$0.00$10.00$10.00
32 Validate data accuracy0%4 days32 hrsTue 11/14/17Fri 11/17/1731Business Analyst$1,615.00Tue 11/14/17Fri 11/17/17$0.00$0.00$0.00$0.00$0.00$1,615.00$1,615.00
33 Wellness Vendor Reporting0%119 days1,984 hrsThu 7/13/17Fri 12/22/17$141,660.00Thu 7/13/17Fri 12/22/17$0.00$0.00$0.00$0.00$0.00$141,660.00$141,660.00
34 Requirements0%108 days640 hrsThu 7/13/17Thu 12/7/17$41,740.00Thu 7/13/17Thu 12/7/17$0.00$0.00$0.00$0.00$0.00$41,740.00$41,740.00
35 Define Business Rules0%32 days256 hrsThu 7/13/17Thu 12/7/17Business Analyst,Project Manager$16,675.00Thu 7/13/17Thu 12/7/17$0.00$0.00$0.00$0.00$0.00$16,675.00$16,675.00
36 Data Mapping0%22 days176 hrsThu 9/28/17Thu 11/30/17Business Analyst,Project Manager$11,475.00Thu 9/28/17Thu 11/30/17$0.00$0.00$0.00$0.00$0.00$11,475.00$11,475.00
37 Report mockups0%8 days64 hrsTue 10/17/17Wed 11/29/17Business Analyst,Project Manager$4,195.00Tue 10/17/17Wed 11/29/17$0.00$0.00$0.00$0.00$0.00$4,195.00$4,195.00
38 Documentation and Current Mockup Layouts0%18 days144 hrsThu 10/19/17Fri 12/1/17Business Analyst,Project Manager$9,395.00Thu 10/19/17Fri 12/1/17$0.00$0.00$0.00$0.00$0.00$9,395.00$9,395.00
39 Requirements Approved0%2 days0 hrsSat 9/2/17Mon 9/4/17$0.00Sat 9/2/17Mon 9/4/17$0.00$0.00$0.00$0.00$0.00$0.00$0.00
40 Report Development0%52 days1,344 hrsFri 10/13/17Fri 12/22/17$99,920.00Fri 10/13/17Fri 12/22/17$0.00$0.00$0.00$0.00$0.00$99,920.00$99,920.00
41 Report file layout data mapping0%16 days128 hrsTue 10/31/17Wed 12/6/17Report Dev 1$11,520.00Tue 10/31/17Wed 12/6/17$0.00$0.00$0.00$0.00$0.00$11,520.00$11,520.00
42 Report UAT0%8 days64 hrsWed 12/13/17Fri 12/22/17Report Dev 1$5,760.00Wed 12/13/17Fri 12/22/17$0.00$0.00$0.00$0.00$0.00$5,760.00$5,760.00
43 Reports Approved by Business Owner/Vendor0%2 days32 hrsTue 12/5/17Wed 12/6/17IS Manager,Business Owner$3,120.00Tue 12/5/17Wed 12/6/17$0.00$0.00$0.00$0.00$0.00$3,120.00$3,120.00
44 QA0%50 days1,120 hrsFri 10/13/17Wed 12/20/17$79,520.00Fri 10/13/17Wed 12/20/17$0.00$0.00$0.00$0.00$0.00$79,520.00$79,520.00
45 Test Case Creation0%22 days176 hrsFri 10/13/17Sat 11/11/17QA$8,800.00Fri 10/13/17Sat 11/11/17$0.00$0.00$0.00$0.00$0.00$8,800.00$8,800.00
46 Test Case Execution0%28 days224 hrsMon 11/13/17Wed 12/20/1745QA$11,200.00Mon 11/13/17Wed 12/20/17$0.00$0.00$0.00$0.00$0.00$11,200.00$11,200.00
47 Deploy Reports to Production0%2 days16 hrsFri 11/10/17Sat 11/11/17Developer$1,440.00Fri 11/10/17Sat 11/11/17$0.00$0.00$0.00$0.00$0.00$1,440.00$1,440.00
48 UAT0%27 days704 hrsSat 11/11/17Mon 12/18/17$58,080.00Sat 11/11/17Mon 12/18/17$0.00$0.00$0.00$0.00$0.00$58,080.00$58,080.00
49 Testing Support0%8 days128 hrsSat 11/11/17Mon 12/18/17ETL Dev 1,Report Dev 1,ETL Dev 2,Report Dev 2$10,560.00Sat 11/11/17Mon 12/18/17$0.00$0.00$0.00$0.00$0.00$10,560.00$10,560.00
50 Remediation0%4 days128 hrsFri 11/17/17Wed 11/22/17ETL Dev 1,Report Dev 1,ETL Dev 2,Report Dev 2$10,560.00Fri 11/17/17Wed 11/22/17$0.00$0.00$0.00$0.00$0.00$10,560.00$10,560.00
51 Production Support0%14 days448 hrsThu 11/23/17Tue 12/12/1750ETL Dev 1,ETL Dev 2,Report Dev 1,Report Dev 2$36,960.00Thu 11/23/17Tue 12/12/17$0.00$0.00$0.00$0.00$0.00$36,960.00$36,960.00
52 Oversight0%92 days147.2 hrsThu 7/13/17Wed 11/15/17$11,410.00Thu 7/13/17Wed 11/15/17$0.00$0.00$0.00$0.00$0.00$11,410.00$11,410.00
53 Project Manager0%92 days73.6 hrsThu 7/13/17Wed 11/15/17Project Manager[10%]$5,890.00Thu 7/13/17Wed 11/15/17$0.00$0.00$0.00$0.00$0.00$5,890.00$5,890.00
54 Architect0%92 days73.6 hrsThu 7/13/17Wed 11/15/17Architect[10%]$5,520.00Thu 7/13/17Wed 11/15/17$0.00$0.00$0.00$0.00$0.00$5,520.00$5,520.00
55 Go-Live0%1 day8 hrsThu 12/21/17Thu 12/21/17$0.00Thu 12/21/17Thu 12/21/17$0.00$0.00$0.00$0.00$0.00$0.00$0.00
56 Go-Live Milestone0%1 day0 hrsThu 12/21/17Thu 12/21/17$0.00Thu 12/21/17Thu 12/21/17$0.00$0.00$0.00$0.00$0.00$0.00$0.00
57 Module Reports in Production- Go live0%1 day8 hrsThu 12/21/17Thu 12/21/17$0.00Thu 12/21/17Thu 12/21/17$0.00$0.00$0.00$0.00$0.00$0.00$0.00
58 Monitor and Control0%107 days48 hrsTue 2/14/17Thu 7/13/17$4,680.00Tue 2/14/17Thu 7/13/17$0.00($4,680.00)$0.00$0.00$4,680.00$4,680.00$4,680.00
59 Support0%107 days48 hrsTue 2/14/17Thu 7/13/17$4,680.00Tue 2/14/17Thu 7/13/17$0.00($4,680.00)$0.00$0.00$4,680.00$4,680.00$4,680.00
60 Define Support Process0%3 days24 hrsTue 2/14/17Thu 2/16/17IS Manager$2,280.00Tue 2/14/17Thu 2/16/17$0.00($2,280.00)$0.00$0.00$2,280.00$2,280.00$2,280.00
61 Review Support Process0%3 days24 hrsFri 2/17/17Tue 2/21/1760Business Owner$2,400.00Fri 2/17/17Tue 2/21/17$0.00($2,400.00)$0.00$0.00$2,400.00$2,400.00$2,400.00
62 Support Process Approved0%0 days0 hrsThu 7/13/17Thu 7/13/17IS Manager,Business Owner$0.00Thu 7/13/17Thu 7/13/17$0.00$0.00$0.00$0.00$0.00$0.00$0.00
63 Closing0%4 days32 hrsWed 12/27/17Sun 12/31/17$2,580.00Wed 12/27/17Sun 12/31/17$0.00$0.00$0.00$0.00$0.00$2,580.00$2,580.00
64 Lessons Learned0%4 days32 hrsWed 12/27/17Sun 12/31/17Project Manager$2,580.00Wed 12/27/17Sun 12/31/17$0.00$0.00$0.00$0.00$0.00$2,580.00$2,580.00

I need some help using this my professor wants me to expand it and change the date to 11/2/15 using this

  • Deliverables:
    • Planning
      • Create project plan
      • Create change management plan
      • Create communications plan
    • System Design
      • Create architecture
      • Design vendor wellness database tables
      • Design wellness vendor reporting
    • Development
      • Build servers
      • Build database tables
      • Build reports
      • Create user documentation
    • Testing
      • Test servers
      • Test database tables
      • Test reports
      • Test server connection to Teradata service.
    • Deployment
      • Launch system
  • Milestones:
    • Initial project plan completed
    • Project charter approved
    • Program code delivered
    • System testing completed
    • User acceptance testing completed
    • Go live delivered
    • Post implementation audit completed
    • Project acceptance sign-off completed
  • Business and Technical Requirements framed in the following manner:
    • The system needs the ability to automatically import data from third party vendors on a weekly and monthly basis, following a similar process:
      • Vendor sends daily data input file for report analytics.
      • The system sends weekly vendor output analytics file (summarization of weekly activities).
      • Vendor evaluates information for approval on correctness of data output and provides additional files (if necessary)
    • Users need the ability to generate reports (e.g. wellness vendor reports) based on third party data;
    • Users need the ability to view and save reports in various formats (e.g. Excel 97-2003 (XLS), Portable Document Format (PDF), or Comma Separated Value (CSV));
    • The system should support MS SQL Server 2008 R2 and Teradata 14 for the database servers
    • The system should use SSRS deployment server for the reporting requirements
    • The system should support MS Visual Studio 2008 Shell, SQL Server Business Intelligence Development Studio and SQL Server Management Studio for the development tools
  • Limits and Exclusions:
    • No user changes will be implemented without going through change management process
    • No updates to prior modules will be performed
    • No new servers, beyond the ones specified in the technical requirements, will be deployed

The 7-2 assignment is another of the key assignments in this course. Examine closely the IT 625 Final Project Milestone Five Guidelines and Rubric. The requirement is for you to leverage what you learned with regards to creating project schedule, the CPM, and risk assessment techniques in order to deliver a Schedule Planning, Risk Planning, and Risk Control Report. For point A, you must submit a Microsoft Project file. For points B and C, you can submit table, a chart or an outline in Word or Excel.

To minimize confusion, when working on the project schedule, assume it is November 2, 2015 and you have just been hired as the new project manager on the Medical Informatics case.

  1. Project Schedule Planning: Using MS Project, develop a comprehensive project schedule plan outlining completion dates, tasks, and relevant milestones. You should include all relevant artifacts that pertain to scheduling aspects of the project plan. In your project schedule plan, you could consider:
    1. Tasks that must be completed before others may begin
    2. Tasks that can be done at the same time
    3. Durations of each task
    4. Planned vs. actual dates
  2. Project Risk Planning: Craft a plan for identifying and monitoring risk. In your plan, you could consider:
    1. The amount of uncertainty in the project and how to deal with it
    2. The threats of greatest concern
    3. How each threat should be dealt with
  3. Risk Control: Determine corrective actions and controls to deal with uncertainty and its impact on the project, based on your risk plan. Ideas to consider may include:
    1. Appropriate quantification of the risks (probability vs. impact)
    2. Contingency funding or time buffers in place to handle threat for now i need help with part 1 project scheduling planning

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!