Question: ID Task Name Duration Start Finish 1 Project 1175 days 4.01.2010 3.07.2014 2 Design 1146,5 days 5.01.2010 27.05.2014 3 Procurement Activities 806.5 days 7.05.2010 7.06.2013
| ID | Task Name | Duration | Start | Finish |
| 1 | Project | 1175 days | 4.01.2010 | 3.07.2014 |
| 2 | Design | 1146,5 days | 5.01.2010 | 27.05.2014 |
| 3 | Procurement Activities | 806.5 days | 7.05.2010 | 7.06.2013 |
| 3.1. | Boat Building Materials | 260 days | 7.05.2010 | 5.05.2011 |
| 3.2. | main drive system materials | 546 days | 7.05.2010 | 7.06.2012 |
| 3.3. | Electronic Systems | 500 days | 7.05.2010 | 5.04.2012 |
| 3.4. | Special Systems | 485 days | 7.05.2010 | 15.03.2012 |
| 3.5. | Ship Electric Systems | 320 days | 8.07.2010 | 28.09.2011 |
| 3.6. | Ship Service Equipments | 320 days | 8.07.2010 | 28.09.2011 |
| 3.7. | Ship Outfitting Equipment | 290 days | 8.07.2010 | 17.08.2011 |
| 3.8. | Ship Owners Take | 180 days | 19.10.2011 | 26.06.2012 |
| 3.9. | Ship Inventory | 202 days | 29.08.2012 | 7.06.2013 |
| 4 | Ship Building | 888 days | 9.02.2011 | 3.07.2014 |
| 4.1. | Hull Building | 228 days | 9.02.2011 | 23.12.2011 |
| 4.2. | Main Hull Building | 208 days | 9.02.2011 | 25.11.2011 |
| 4.3. | Block1 | 51 days | 9.02.2011 | 20.04.2011 |
| 4.4. | Block2 | 51 days | 18.02.2011 | 29.04.2011 |
| 4.5. | Block3 | 51 days | 1.03.2011 | 10.05.2011 |
| 4.6. | Block4 | 51 days | 10.03.2011 | 19.05.2011 |
| 4.7. | Block5 | 51 days | 21.03.2011 | 30.05.2011 |
| 4.8. | Block6 | 51 days | 30.03.2011 | 8.06.2011 |
| 4.9. | Block7 | 51 days | 8.04.2011 | 17.06.2011 |
| 4.10. | Block8 | 51 days | 19.04.2011 | 29.06.2011 |
For s shipbuilding project, the completion time of each events and, the relationship between the activities (predecessors-dummy) are given in the table According to the bar chart on the given table, total work time-schedule is shown with a bar for each project activity that shows passage of time a. Draw the Project network as Activities On Arrow (AOA), b. Draw the Project network as Activities On Node (AON), c. Show the Critical Paths on AOA network, d. Show the Critical Paths on AON network, e. Analyze the paths and show the completion time of the total project on the networks,