Question: Identify an accurate statement about a PERT ( program evaluation and review technique ) chart. It was first developed by Henry Gantt. It maps tasks

Identify an accurate statement about a PERT (program evaluation and review technique) chart.
It was first developed by Henry Gantt.
It maps tasks exclusively in line and bar graphs.
It indicates the most optimistic estimates of the time to complete a project under the best conditions.
It focuses on the shortest path or the critical path taken to complete an activity.