Question: Identify Following cost as either Variable Cost, Fixed Cost, Mixed Cost, Step Cost : 1. Factory direct labor costs 2. Factory receptionist 3. Utilities for
Identify Following cost as either Variable Cost, Fixed Cost, Mixed Cost, Step Cost :
1. Factory direct labor costs
2. Factory receptionist
3. Utilities for the factory
4. Rent for the factory
5. Fabric to make the hoodies
6. End of summer staff party for all factory workers which is prebooked in advance each year and includes venue rental, food, and alcohol.
7. Factory supervisor costs (each supervisor can supervise either the day shift or the night shift if a second shift is required)
8. Factory security costs from an external vendor who charges a base fee per month plus a standard fee per visit
9. Lease costs for the packaging machines which can each package 5,000 hoodies per month
10. Depreciation for the cutting and sewing machines
Step by Step Solution
There are 3 Steps involved in it
Factory direct labor costs Variable Cost 2 Factory receptionist Fixed 3 Utiliti... View full answer
Get step-by-step solutions from verified subject matter experts