Question: Identify the attribute that is not normally associated with the job of functional manager. A. The functional manager is usually a generalist in the area
Identify the attribute that is not normally associated with the job of functional manager.
| A. | The functional manager is usually a generalist in the area being managed | |
| B. | The functional manager is responsible for deciding what resources will be devoted to accomplishing the task | |
| C. | The functional manager is administratively responsible for deciding how something will be done | |
| D. | The functional manager is responsible for deciding who will do the work |
The project manager should be ________.
| A. | A direct, technical supervisor knowledgeable in the technology of the process being used | |
| B. | Both generalist/facilitator and have a high level of technical competence in the science of the project | |
| C. | A facilitator and specialist with technical credibility | |
| D. | A technical specialist competent in principles of robust design |
When managing a project, the project manager is responsible for ________.
| A. | Planning and controlling the project | |
| B. | Planning, staffing, and executing the project | |
| C. | Organizing, staffing, budgeting, directing, planning, and controlling the project | |
| D. | Organizing, designing, staffing, executing, auditing, and controlling the project |
During the ________ stage of the project lifecycle, there is no significant difference in the importance that project managers place on the three goals of cost, time, and performance.
| A. | Initiation stage | |
| B. | Design or formation stage | |
| C. | Buildup stage | |
| D. | Final stage |
According to the authors, of all the characteristics desirable in a project manager, ________ is the most important
| A. | Availability | |
| B. | A strong technical background | |
| C. | A person who can keep the project team happy | |
| D. | Drive to complete the task |
A party to a conflict will usually be satisfied when the level of frustration has been ________.
| A. | Totally eliminated by dominating the other party | |
| B. | Lowered to the point where no action against the other party is contemplated | |
| C. | Lowered because the party realizes the hopelessness of continuing the conflict | |
| D. | Eliminated because the party has surrendered to the other party |
Most of the conflicts that involve the organization and outsiders have to do with ________.
| A. | Interpersonal differences | |
| B. | Cultural differences | |
| C. | Contractual obligations | |
| D. | Property rights and contractual obligations |
Conflicts within the organization typically differ from conflicts with outsiders in one important way. As far as the organization is concerned, these conflicts are ________.
| A. | Conflicts between opponents | |
| B. | Conflicts between allies | |
| C. | Trivial conflicts | |
| D. | Conflicts that should be suppressed |
If a resource conflict arises between two high-priority projects, precedence is typically given to the project with the ________.
| A. | Earliest due date | |
| B. | Fastest completion time | |
| C. | Biggest revenue stream | |
| D. | Lowest cost to complete |
The need to manage technical interfaces and to correct incompatibilities is likely to create technical conflicts during the ________ phase of the project lifecycle.
| A. | Project formation | |
| B. | Project buildup | |
| C. | Main program | |
| D. | Project phase out |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
