Question: Identify the critical path, include the latest start and the latest finish column, include the early start and early finish column for a rad construction
Identify the critical path, include the latest start and the latest finish column, include the early start and early finish column for a rad construction for 103 days for the following resources and columns below:
-initial approaved 5 days
-council approved 5 days
-environmental approaved 5 days
-site reconnaissance 6days
-legal aspect of site 1 day
-on ground survey 1
-design work 3days
-earth work design 1 day
-pavement design 1 day
-psp design 1 day
-design approval
-traffic management15 days
-road signing record 1day
-installation of temporary light 1day
-equipment 6 days
-material 9 days
-main power 6 days
-environmental inspection 1 day
-cultural, heritage and management1 day
-earth work 4 days
-road excavator6 days
-excavation for culvert pipes2 days
-installation of fibre2 days
-laying of electrical3 days
-back fill work2 days
-pavement placement3 days
-spraying of bituminus1 day
-laying of asphalt1 day
-compaction with roller 2 days
-placement of surface base 1 day
-signage installation 2 days
-lights installation 2days
-line marking1 day
-hand over 1 day
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
